Palm Beach sports field lights

Client:
Palm Beach Soccer Club
Date:
June - November 2021
Type of Project:
Sports field lighting upgrade and pole repairs (2 x fields)
Project Value:
$110,000.00

Project Description

  • Field 3 – Upgrade of light fitting to ARECA LED re-suing existing pole
  • Field 2 – Repairs to rust-damaged poles and upgrade of light fitting to ARECA LED.

Platinum Electrical was been awarded the contract to upgrade the field lighting at Palm Beach Soccer Club. The project, which was valued at $110,000, will involve the installation of new ARECA LED light fittings on both Field 2 and Field 3.

In addition, Platinum Electrical also carried out repairs to the poles on Field 2 that have been damaged by rust. The project was completed in November 2021.

Platinum Electrical has a proven track record in delivering high-quality sports field lighting projects, and we are confident we have meet the expectations of the Palm Beach Soccer Club.